Metsä Fibre has received the new district heating station at its Rauma pulp mill, entering the commissioning phase to supply up to 20% of the local heating demand by December 2026.

November 14, 2026
3 min read

Metsä Fibre, part of Metsä Group, and local energy provider Rauman Energia have reached the final stages of their joint project to integrate industrial waste heat into the municipal district heating network in Rauma, Finland. The new district heating station has arrived at the pulp mill site, marking the transition into the connection, testing, and commissioning phase. The system is scheduled to begin heat production in December 2026.

The project captures unutilized waste steam from the mill's recovery boiler, a core component of the chemical recovery cycle where black liquor is combusted. While the generated steam primarily powers the mill's turbine, generator, and internal processes, the facility produces more energy than it consumes. Previously, excess steam was cooled in condensers and dissipated through cooling towers. The new station will recover this thermal energy and transfer it directly to the local heating grid.

Preparations for the integration have been ongoing since 2025, when connection points were installed in the mill's steam and condensate systems during the annual maintenance shutdown. Construction of a 2.5-kilometer district heating pipeline began in January 2026 and was completed in the spring. Once fully operational, the recovered heat is expected to cover between 10% and 20% of Rauman Energia's total heat demand.

Jaakko Rautala, Production Manager at Metsä Fibre's Rauma pulp mill, noted that the project improves the facility's overall energy efficiency by reducing the energy previously required to cool the excess heat. For Rauman Energia, the decentralized heat source adds critical production capacity, particularly during disruptions or peak demand periods, potentially reducing the need to activate oil-fired backup heating plants.

Testing of the newly installed station will commence in early December, with the goal of achieving full production use by the end of the month. The initiative aligns with broader industry efforts to optimize energy efficiency in integrated pulp and sawmill complexes by monetizing production side streams and supporting local infrastructure.

Enjoying this article?

Register free to save and share.

Tags

#Metsä Fibre
#Metsä Group
#Rauman Energia
#Pulp Mill
#Waste Heat Recovery
#District Heating
#Energy Efficiency
#Finland
#Sustainability
#Celulosa