Pakka sets December start-up for PM4 machine after completing pulp expansion
Pakka Limited confirms the start-up of its new PM4 paper machine for December 2026, completing the industrial expansion of Project Jagriti in India.
Indian manufacturer Pakka Limited has established December 2026 for the start-up of its new Paper Machine 4 (PM4), marking the final major industrial milestone of its modernization and expansion plan known as Project Jagriti. With the pulp mill expansion already completed, the company is now focusing its efforts on stabilizing auxiliary equipment and preparing the market for its upcoming production capacity.
The technical roadmap of the project demonstrates a phased integration. During October, Pakka successfully fired up the new recovery boiler and the 15 MW cogeneration turbine. Both units are currently in the stabilization phase, a critical step in any integrated paper mill before subjecting the main machine to continuous workloads. The decision to schedule the PM4 start-up for December aligns with a strategy of thoroughly testing each component, aiming to prevent unforeseen downtime once the cylinders begin to turn.
Seeding the market ahead of production
The most notable aspect of Pakka's strategy is not just the hardware installation, but how they are managing preliminary demand. The company has not waited for PM4 to become operational to commercialize its flexC base paper, a fiber-based flexible packaging material intended for applications such as release liners, heat-sealable bags, and food pouches.
Currently, Pakka is already placing over 500 tonnes per month of equivalent flexC grades in the market through outsourced production. This volume represents approximately 17% of PM4's total future capacity, meaning the machine will come online with an already seeded customer base. Furthermore, the company recently completed pilot trials in Europe, validating the product's technical specifications in highly demanding markets.
Transitioning to commercial output
The industrial timeline establishes a clear distinction between technical start-up and commercial availability. While December 2026 will mark the beginning of machine trials, full-scale commercial production is targeted for January 2027. Pakka's management anticipates a gradual learning and ramp-up curve, projecting a capacity utilization of 30% to 50% during the initial months, before stabilizing at levels above 75% for the 2028 financial year.
This shift toward specialty grades aligns with the recent performance of its Wrap & Carry division, which already allocates nearly 30% of its sales to high-value-added papers and exports. A recent example of this diversification is an initial order of approximately 200 tonnes secured with Reliance for interleaving paper used in solar glass manufacturing. With the pulp and energy infrastructure now operational, PM4 represents the final piece for Pakka to consolidate its transition toward the integrated manufacturing of specialty flexible packaging at an industrial scale.